SR163 NGET CDM Practice Questions – Set 1
Results
Congratulations – You Passed! 🎉
You’ve demonstrated a good understanding of CDM requirements and how they apply to National Grid Electricity Transmission projects.
Working safely and compliantly on NGET projects requires a clear understanding of roles, responsibilities, documentation, and the practical application of CDM principles. This result shows you’re heading in the right direction.
Want to build on your knowledge and confidence even further?
Our CDM Awareness & National Grid Supplier Requirements (SR/163) course provides practical guidance on applying CDM 2015 requirements within National Grid projects.
Find out more here:
CDM Awareness & National Grid Supplier Requirements (SR/163) Course
Not Quite This Time 👍
CDM and National Grid requirements can be challenging, especially when applying them to real project situations.
This quiz is designed to highlight areas where your knowledge may need a little more work. Take some time to review the topics you found difficult and have another go; you might be surprised how quickly your score improves.
Looking to strengthen your understanding of CDM on National Grid projects?
Our CDM Awareness & National Grid Supplier Requirements (SR/163) course covers key responsibilities, documentation, compliance requirements, and practical application to help you work confidently and safely.
Find out more here:
CDM Awareness & National Grid Supplier Requirements (SR/163) Course
#1. What is the primary purpose of NG/ET/SR163, Management of Works?
#2. Which statement best describes the main construction-phase responsibility of a Principal Contractor under NG/ET/SR163?
#3. Which information should be incorporated into the Construction Phase Plan under NG/ET/SR163?
#4. When should the proposed Contractor Representative or Principal Contractor Representative normally be submitted for acceptance?
#5. What should normally happen if the approved Contractor Representative or Principal Contractor Representative is unexpectedly unavailable?
#6. How should Pre-Construction Information be used on an NGET project?
#7. When should the Construction Phase Plan normally be provided to the Client Representative for acceptance?
#8. What is the main purpose of the Health and Safety File?
#9. Which arrangement most accurately reflects NGET requirements for temporary works?
#10. What time should normally be provided to the NGET Project Supervisor before work takes place?
#11. NGET directly appoints a specialist contractor to carry out construction work within an area controlled by the Principal Contractor. Which statement is correct?
#12. Which statement correctly describes the relationship between a National Grid Safety Document and the Contractor’s construction safety arrangements?
#13. What is the correct process where work may require a National Grid Safety Document?
#14. Which statement best describes the establishment of a CDM demarcation zone?
#15. What should happen when the boundary of a CDM demarcation zone changes?
#16. What is the main purpose of the Site Out of Hours CDM Communications Sheet?
#17. Which arrangement most accurately reflects NG/ET/SR163 requirements for excavation within an operational substation?
#18. What is the principal purpose of the four-week lookahead required by NG/ET/SR163?
#19. Which statement correctly describes the NGET Pre-Site Start Meeting?
#20. An important project milestone has been brought forward. What is the most appropriate CDM response?