If you’re a contractor working on public highways, understanding Section 74 of the New Roads and Street Works Act (NRSWA) is essential. This legislation allows highway authorities to apply penalties when street works overrun their agreed duration. In short: if your roadworks take too long, you could be fined.
Here’s a practical breakdown of what Section 74 means, how it works, and how to avoid unnecessary costs.
I am a contractor and have been warned about receiving a Section 74 - what is it?
Section 74 of the NRSWA allows highway authorities to impose financial penalties on utility companies and contractors who carry out street works that exceed their agreed schedule without good reason. The aim is to reduce delays and ensure roads are reopened as soon as possible.
In simple terms: if you're digging up the road and you take too long, you pay.
Before Section 74 was introduced, there were few incentives for utility companies to complete work quickly. Roads could be blocked for weeks, frustrating drivers, harming local businesses, and increasing traffic congestion.
By introducing daily fines for overruns, Section 74 encourages better planning and more efficient execution of works.
Here’s a step-by-step breakdown of how Section 74 operates:
Charges vary between authorities and depend on:
In general:
Not all overruns automatically result in penalties. You may be exempt if delays are caused by:
Additionally, Section 74 only applies when formal notice and timing agreements are in place. Emergency works, for example, may follow different rules under NRSWA.
Section 74 represents a key tool in balancing infrastructure work with public convenience. It may not eliminate delays altogether, but it holds contractors and utility providers accountable for efficient roadwork execution.
That’s a win for:
Understanding your obligations under Section 74 can help you avoid costly penalties and keep your projects on track. With proper planning, communication, and execution, you can meet your deadlines, and keep the local roads moving.
Want to avoid Section 74 fines? Contact our team for training options and ensure you and your team are up to date with street works compliance.
If you are interested in Streetworks courses, find out more here.
Registered Office:
Unit 78, Avenue Q
Stoneleigh Park
Kenilworth
Warwickshire
CV8 2LG
Registered company number: 08612308
© 2014 - 2025 Pragmatic Consulting Ltd. All rights reserved.
Home | Privacy Policy | Cookies | Site map | Admin